Profile
Highly capable, Ex.General Manager (Electrical), with over 25 years’ experience in managing major projects of installation, testing, commissioning and maintenance of electrical systems (onshore) including mega LSTK project of Storage & Transportation of HFHSD & ATF and Solar Projects, maintenance and laying of crude oil and gas pipe line and water injection line. In addition to above, possess 10 years’ versatile expertise of installation, testing, and troubleshooting of Hill Graham SCR system, commissioning and maintenance of electrical systems at onshore & offshore drilling rigs; Seeking a managerial assignment as……
GENERAL MANAGER / HEAD OF ENGINEERING MAINTENANCE / PROJECT MANAGER / VP
(Oil & Gas Industry /Power/Solar/Drilling)
Dynamic and results-driven Management Executive with 25+ years of insightful experience, leading & managing variety of challenging projects, predominantly of the installation, testing, commissioning and maintenance of electrical systems at onshore. In addition to above 10 years’ in-depth experience of commissioning, testing, maintenance of electrical system on offshore drilling rigs. And provided operations support and management of electrical power supply, trouble shooting on drilling Rigs. Well versed in preparation of Feasibility and Techno Commercial Project Report and execution of Solar and Hybrid Systems of Alternate Energy. Possess a long track record of ensuring timely completion of a number of electrical projects at different locations in Maharashtra, Assam, Gujarat, with highest quality, within budget by effectively organizing, managing and utilizing all the available resources and able to efficiently lead teams to undertake execution and commissioning of large electrical projects; proven technical, interpersonal communication and training skill; strong work ethic with ability to work under pressure and take on difficult and complex challenges.
PROFESSIONAL SYNOPSIS
• A keen strategist, planner and implementer with expertise in organizing & devising all aspects pertaining to construction of electrical power transmission system, sub-stations and Earthling System.
• Highly skilled in executing the project activities in compliance with HSE regulations, and other stipulated regulatory authorities’ requirements, together with the implementation and application of International Standards and Regulations.
• Decision and result oriented leader ,top performing team player with strong liason & communication skills with the ability to advise the project management team & client on Technical issues.Effectively managed team performance through coaching, mentoring,problem solving and interpersonal interventions.
JOB PROFILE & DURATION SCAN
• For a period of 1 year:
o Managed the operation and maintenance of 33 kv electrical substation and construction of 11kv power transmission line and looked after the job of earthling system for 400kv power transmission line
• For a period of 10 years:
o Managed the operation and maintenance of electrical systems, SCR systems including trouble shooting on drilling rigs, centralized accommodation, air conditioning, communication systems, utilities on jack up rig - Sagar Samrat, Sagar Jyoyi and Sagar Pragati.
o Executed the construction of rig Sagar Uday at Mangalore dock yard.
• For a period of 22 years-
o coordinated the operation and maintenance of electric system of on-shore drilling rigs & production installation including the installation & commissioning of electrical equipment on production installation and electrical power supply to SRP ststem,
o Layed the pipe line for crude oil, gas & water injection along with its maintenance through CP.
o Worked as project coordinator to execute the construction,testing and commissioning of electrical substation. and installation along with commissioning of firefighting system.
o Prepared the estimate and accomplished construction, inspection & commissioning of firefighting system and GGS at Gamij, Limbodra, Wadu, Paliyad, and Kalol including electrical system.
o Worked as Project Manager for LSTK project for construction of 10,000 kl HFHSD and 350 kl of ATF storage facilities including transportation of HFHSD and ATF through pipe lines with the execution of firefighting system project.
o Secured the approval & certificates from different statutory authorities.
• For a period of 3 years-
o Prepaired the feasibility and techno commercial project report for solar and hybrid systems of alternate energy & project construction.
PROJECTS
• 2014 - 2016 (2 years)
5) Efficiently executed the project of Laying of crude oil, Gas pipe line & Water injection pipe line in PIMD (C&M) on an average of 15 kms per month & Maintenance of same underground pipe line through CP system.
• 2012 - 2013 (1 years)
4) Preparation of Feasibility & Techno Commercial 1Mwe Project Report & Execution for Solar & Hybrid system of Alternate Energy.
• 2007 - 2010 (3 years)
3) Worked as Project Manager for LSTK project for construction of 10,000 kl HFHSD and 350 kl of ATF storage facilities including transportation of HFHSD and ATF through pipe lines with the execution of firefighting system . Got licences from ststutories authourities ie Forest, factory inspector,environment office & PETROLEUM AND EXPLOSIVES SAFETY ORGANISATION (PESO) GOVT OF INDIA, NAGPUR.
• 2000 - 2005 (5 years)
2) Palyed a key role in Construction, Equipments testing & commissioning of GGSs at Limodara, Wadu, Paliyad & Gamij, Kalol which contributed in increase of crude oil production including Fire fighting system & Electrical Sub station.
• 1989 - 1990 (1 years)
1) Executed the construction of rig Sagar Uday at Mangalore dock yard.
ACHIVEMENTS
--------------------------------------------------------------------------------------------------------------------
• 4) Commissioned LSTK project for construction of 10,000 kl HFHSD and 350 kl of ATF storage facilities including transportation of HFHSD and ATF through pipe lines with the execution of firefighting system . Got licenses from statutory authorities ie Forest, factory inspector, environment office & PETROLEUM AND EXPLOSIVES SAFETY ORGANISATION GOVT OF INDIA, NAGPUR Efficiently executed the project of Laying of crude oil, Gas pipe line & Water injection pipe line in PIMD (C&M) on an average of 15 kms per month & Maintenance of same underground pipe line through CP system.
• 3) Designed, Estimation, Construction & commissioning of Electrical substation. Preparation of Feasibility & Techno Commercial 1 MWe Project Report & Execution for Solar & Hybrid system of Alternate Energy.
• 2) Constructed & Commissioned the GGSs at Limodara, Wadu, Paliyad , Gamij &Kalol which contributed an increase in crude oil production .
1) Introduced necessary schedule maintenance & conditioning-monitoring system to ensure the 100% availability of Electrical & Mechanical Equipment on Offshore & Onshore Drilling Rigs. Tested the equipment & commissioned on Rig S/ Pragati in Mumbai offshore when it towed to offshore from Dubai Drydock.Executed the construction of rig Sager Uday at Mangalore dock yard.Held Managerial Roll in contingency plan at the time of Blow out on Drilling Rig E1400-8XCEndi19969226404 EXPERIENCE EDUCATION